The County of Santa Barbara, Board of Supervisors has awarded $3.4 million for the 2010/2011 County Wide Preventive Maintenance Application of Scrub Seal and Micro-Surfacing project. Important State and local funds are being used towards a comprehensive, county wide pavement preservation program by the Santa Barbara County Public Works Department.

“This important work extends the life of the roads and helps provide the traveling public with a clearer path, smoother ride and a safer trip!” said Scott McGolpin, Public Works Director. State Propositions 42 and 1B are providing the majority of the funding for this project, in addition to Measure D and State Gas Tax funds. These funds are being used to help maintain, preserve, and improve roads throughout the County of Santa Barbara.

Approximately 57 lane miles will be resurfaced with the construction of this project. Construction of this project requires a two step process. The first application will be a scrub seal, which will fill any cracks or voids in the pavement. This will be followed up with the application of a micro surfacing being placed on top of the scrub seal to provide a smooth riding surface. Construction will begin in the northern section of the county with the project finishing in the southern section of the county. A list of streets included in this project is listed below.

Construction is scheduled to begin June 6, 2011 and should be completed by late August, 2011, contingent upon weather conditions. Windsor Fuel Company was awarded the contract for the County Wide Preventive Maintenance Application of Scrub Seal and Micro Surfacing, and the County’s Public Works Department will inspect and administer the construction of this project.

Construction will occur Monday thru Friday between the hours of 7:00 AM and 5:00 PM. The Department encourages the travelling public to use an alternate route when possible. Drivers should be aware of reduced speed zones and increased traffic control when driving through the construction sites.

Public Works Department officials wish to thank local residents, pedestrians and the travelling public for their patience and cooperation during the construction of this project

Street Between SUMMERLAND / CARPINTERIA

Nidever Road

Highway. 192

Via Real

Shelby Street

East End

West End

Stanley Park Road

Highway 150

Private Road

Wallace Avenue

Evans Avenue

Finney Street

NORTH OF SANTA BARBARA CITY LIMITS

Ashley Road

Highway 192

East Mountain Drive

Barker Pass Road

Highway 192

Paso Robles Drive

Butterfly Lane

Middle Road

City Limit

Cold Springs Road

Highway 192

East Mountain Drive

High Road

Butterfly Lane

Middle Road

Hill Road

Butterfly Lane

Olive Mill Road

East Mountain Drive

San Ysidro Lane San Ysidro Road

East Mountain Drive

Ashley Road

Brook Tree Road

Oak Road

Mesa Road

Hot Springs Road

Paso Robles Drive

Stoddard Lane

Chelham Way

Puesta Del Sol

City Limit

Mission Canyon Road

NEAR GOLETA

Avenida Pequena

Las Perlas Drive

Cathedral Oaks Road

Calle Cristiobal

Calle Morelia

West End

Calle Morelia

Calle Cristiobal

San Ricardo Drive

Calle Real

Turnpike Road

Pebble Hill Place

Calle Real

Patterson Avenue 880 ft. West of Patterson Avenue

Cathedral Oaks Road

Turnpike Road

El Rodeo Road

Cathedral Oaks Road

Patterson Avenue City Limit

Puente Drive

Hollister Avenue

Via Huerto

San Ricardo Drive

Hollister Avenue

San Vicente Drive

Sandpiper Lane

Vieja Drive

West End

Sandspit Road

William Moffet

City Limit

Turnpike Road

Calle Real

Cathedral Oaks Road

Veronica Springs

Modoc Road

Veronica Place

Vieja Drive

Via Huerto

South End

ISLA VISTA

Del Playa Drive

160 ft. E. El Embarcadero 250 ft. West of El Embarcadero

El Colegio Road

Storke Road

400 ft. West of Camino Del Sur

El Embarcadero

Del Playa Drive

Embarcadero Del Mar

Embarcadero Del Mar

El Embarcadero

816 ft. North of El Embarcadero

Embarcadero Del Norte El Embarcadero

813 ft. North of El Embarcadero

Glenn Anne Road

Cathedral Oaks

North End

Storke Road

El Colegio Road

625 ft. North of El Colegio Road

Street Between SANTA YNEZ

Armor Ranch Road

Highway 154

Happy Canyon Road

Baseline Avenue

Edison Street

3 Miles West of Happy Canyon Road

Foxen Canyon Road

Highway 154

2 Miles North of Hwy 154

Fredensborg Cyn. Road City Limit

North End

Stagecoach Road

West Camino Cielo 2 Miles North of South End

LOS ALAMOS

Main Street

Den Street

West End

MISSION HILLS

Purisima Road

1.4 Miles W. Mission 4,100 ft. West of Mission Gate Road

GUADALUPE

Simas Street

Highway 166

Betteravia Road

ORCUTT

Amberley Place

Old Mill Lane

East End

Berrywood Drive

Stratford Street

South End

Claybrook Court

Patterson Road

End

Francine Lane

Hillview Road

Bradley Road

Frontage Road #5593

Santa Maria Way South End

Hope Terrace

Hummel Drive

End

Lakeview Road

Bradley Road

Orcutt Road

Mi Tierra

Hummel Drive

End

Silver Leaf Drive

Foster Road

Fairmont Avenue

Stillwell Road

Clark Avenue

775 ft. South of Clark Avenue

Townsend Lane

Orcutt Road

End

Union Valley Parkway

Boardwalk Lane

Hummel Drive

Wendy Way

Francine Lane

End

Solomon Road

200 ft. E. of Hwy. 1 Kapalua Drive