The City of Santa Barbara has hired Howard Ridley Company, Inc. as the contractor for the Lot 9 – Lobero Parking Garage – Traffic Coating and Sealing Project located at 921 Anacapa Street, directly behind the Lobero Theatre. This project is scheduled to start on Monday, October 28, 2013 and completion is anticipated by Tuesday, November 26, 2013.

The project consists of repair/replacement of the existing traffic coating on the mid-level concrete slab and sealing all joints/cracks on the roof level of the parking structure. The work will seal and preserve the integrity of the concrete roof slab and prevent rainwater from leaking into the businesses below. During construction, the Contractor will maintain public access to the garage stairwells and elevators, adjacent paseos, and surrounding businesses. One level of the structure will always be available for public parking during construction.